Dover, Strafford County
Wastewater Treatment Facility Secondary Clarifier No. 3
Funding recipient: Dover
What the funding paid for
The project includes the construction of a third secondary clarifier and fourth return activated sludge (RAS) pump at the wastewater treatment facility (WWTF). This project will increase the reliability of treatment through equipment redundancy at the WWTF and will also increase the ability of the WWTF to provide treatment during periods of peak flows associated with wet weather.
Funding
$6,400,000
- Clean Water State Revolving Fund: $6,400,000
- Commitment date: Sept. 21, 2022
- Project type: Infrastructure (Construction)
- Water system: Wastewater
- Project number: 334200-22
- Location: Approximate
- Record source: EPA public records