New Durham, Strafford County

New Well House and Distribution Upgrades Project

Funding recipient: Copple Crown Village District

What the funding paid for

The design and construction of an addition at the upper pressure zone/Station 2 building to accommodate new atmospheric and pressure tanks, treatment system, backwash discharge, booster pumps with new electrical and mechanical piping; connection of the existing waterline and electrical line from the well to the building; construction of a new access road; installation of new pressure reducing valve structures and water main distribution upgrades throughout the system, as needed. Funds will also be used for design, bidding and construction of new pressure tanks and booster pumps at Stations 1 and 3.

Funding

$265,200