New York
Where the state’s revolving fund money for water went, project by project.
$5.9 billion committed to 718 drinking water and clean water projects.
- Drinking water: $831 million
- Clean water: $5.1 billion
- Grants and forgiven principal: $614 million
- Latest agreement: June 30, 2025
The 25 largest projects
- C2-5209-40-05: NEWTOWN CREEK<br>;<br> C2-5201-20-12: Wards Island<br>;<br> C2-5203-15-02: Bowery Bay<br>;<br> C2-5203-21-01:Bowery Bay<br>;<br> C2-5204-01-05:Tallman Island<br>;<br> C2-5205-20-04: JAMAICA<br>;<br> C2-5206-19-01: 26th Ward, Bowery Bay, Tal: NYCMWFA. $283 million, clean water. July 23, 2020. STP UP [NC-41 RESIDUALS BLDG.] Project NC-41. Construction of Central Residuals Building Upgrades associated with the Newtown Creek Wastewater Treatment Plant upgrades to improve water quality in Newtown…
- C2-5203-15-04 - Bowery Bay<br>;<br> C2-5203-21-04 - Bowery Bay<br>;<br> C2-5209-12-00 - Newtown Creek<br>;<br> C2-5212-19-02 - Rockaway<br>;<br> C2-5225-16-08 - Gowanus Pump Station<br>;<br> C2-5225-86-00 - Prospect Expressway Pump Station<br>;<br> C2-523: NYCMWFA. $274 million, clean water. June 16, 2022. STP REHAB [BB-61, 64, 65 Main Sewage Pumps] Project BB-61/64. Planning, design, and construction for main sewage pump replacement at the Bowery Bay Wastewater Treatment Plant to improve water quality in the Rikers…
- SW SD #3, BERGEN PT: Suffolk County. $211 million, clean water, $26.9 million in grants and forgiven principal. Sept. 15, 2016. OS REHAB [CP8108 (NON-CONSTRUCTION COSTS & BASE SRF FUNDS ONLY)] Planning and design costs for a new ocean outfall at the Bergen Point WWTP to the barrier island to provide resiliency and damage mitigation during…
- Chemung County Sewer Districts: Chemung County. $174 million, clean water, $25.0 million in grants and forgiven principal. April 18, 2024. STP REPL [Consolidation of two WWTP at MILTON STREET] Planning, design, and construction of single consolidated treatment plant at the Milton Street Wastewater Treatment Facility to protect water quality in the Chemung…
- BAY PARK SEWER DISTRICT: Nassau County. $149 million, clean water. March 18, 2021. BAY PARK STP DIVERSION TO CEDAR CREEK (CONSTRUCTION MANAGEMENT COSTS) Construction management costs for diversion of Bay Park effluent to Cedar Creek STP to provide resiliency, flood mitigation and improve water…
- City of Long Beach: Long Beach, City of. $149 million, clean water. Nov. 16, 2023. Construction of the Long Beach Sewage Treatment Plant conversion into a pump station to provide resiliency, flood mitigation, and improve water quality in Reynolds Channel. Bay Park Sewer Connection and Long Beach WPCP…
- C2-5201-31-00 - Wards Island<br>;<br> C2-5203-15-03 - Bowery Bay<br>;<br> C2-5203-21-02 - Bowery Bay<br>;<br> C2-5212-19-00 - Rockaway<br>;<br> C2-5218-04-02 - Newtown Creek<br>;<br> C2-5225-16-06 - Gowanus Pump Station: NYCMWFA. $130 million, clean water. June 16, 2022. STP REHAB [WI-281 Final Settling Tank Reconstruction] Project WI-281. Design & Construction of 39 Final Settling Tanks and associated modifications to improve settling performance at the 5 Batteries of Wards Island…
- Chemung County Sewer Districts: Chemung County. $105 million, clean water. Feb. 25, 2025. STP REPL [Consolidation Wastewater Treatment at Milton Street] Planning, design, and construction of single consolidated treatment plant at the Milton Street Wastewater Treatment Facility to protect water quality in…
- BAY PARK SEWER DISTRICT: Nassau County. $98.9 million, clean water. Oct. 13, 2022. OS [BAY PARK STP DIVERSION TO CEDAR CREEK (CONSTRUCTION COSTS)] Construction costs for diversion of Bay Park effluent to Cedar Creek STP to provide resiliency, flood mitigation and improve water quality in Reynolds…
- SW SD #3, BERGEN PT: Suffolk County. $96.8 million, clean water. Dec. 6, 2022. OS REHAB [CP8108 (BASE SRF FUNDS ONLY)] Construction costs for a new ocean outfall at the Bergen Point WWTP to the barrier island to provide resiliency and damage mitigation during future storm events and to improve…
- City: Auburn, City of. $83.0 million, clean water, $25.0 million in grants and forgiven principal. July 25, 2024. ORF, STP UP [Biosolids and Wastewater Process Improvements - Construction] Planning, design, and construction of biosolids and wastewater process improvements at the City of Auburn Wastewater Treatment Plant to protect…
- C2-5201-31-01 - Wards Island<br>;<br> C2-5203-21-03 - Bowery Bay<br>;<br> C2-5204-01-06 - Tallman Island<br>;<br> C2-5206-19-02 - 26th Ward, Bowery Bay, Tallman Island, Wards Island, Jamaica<br>;<br> C2-5212-19-01 - Rockaway<br>;<br> C2-5225-16-07 - Gowan: NYCMWFA. $79.2 million, clean water. June 16, 2022. STP REHAB [WI-281 Final Settling Tank Reconstruction] Design and construction of 39 Final Settling Tanks and associated modifications to improve settling performance at the 5 Batteries of Wards Island WPCP to improve…
- WALWORTH (T), PALMYRA (V), MACEDON (T), MARION (T): Wayne County W&S Authority. $75.5 million, clean water. Sept. 24, 2020. COLL,STP Planning, design, and construction of a regional wastewater treatment plant in western Wayne County to maintain water quality in the NYS Barge Canal.
- PHASE 1 & 2A: Oneida County. $73.4 million, clean water. Sept. 24, 2020. STP UP [WWTP Contract 2, 6, 7, 8; SCPS Contract 4 & 5; Barnes Ave PS] Planning, design, and construction of WWTP Upgrades Phase 6A to improve water quality in the Mohawk River.
- BAY PARK SEWER DISTRICT: Nassau County. $66.6 million, clean water. Dec. 14, 2023. OS [BAY PARK STP DIVERSION TO CEDAR CREEK (CONSTRUCTION COSTS)] Construction for diversion of Bay Park effluent to the Cedar Creek Sewage Treatment Plant to provide resiliency, flood mitigation and improve water…
- ONONDAGA LAKE IMPROVEMENT PROJECT: Onondaga County. $57.4 million, clean water. Dec. 8, 2011. CSO(CLINTON CSO ABATEMENT PHASE II - STORAGE/GREEN INFRASTRUCTURE) Elimination of combined sewer overflows as part of the Onondaga Lake Improvement Project to improve water quality in Onondaga Lake.
- NYC Catskill Aqueduct Tap Connection - Phase 2: Kiryas Joel (V), Monroe. $57.2 million, drinking water. Feb. 18, 2021. DWSRF 18208B is Phase 2 of DWSRF Project #16906. This project is for the financing of costs associated with the planning, design, and construction of the approximately six and a half miles of transmission main referred…
- Phase 6A: Oneida County. $55.0 million, clean water. June 13, 2019. STP UP Planning, design, and construction of WWTP Upgrades Phase 6A to improve water quality in the Mohawk River.
- BIRD ISLAND WWTP: Buffalo Sewer Authority. $52.9 million, clean water, $22.9 million in grants and forgiven principal. July 21, 2022. STP IMP [SECONDARY] Planning, design and construction of hydraulic and aeration system improvements at the Bird Island WWTP to protect water quality in the Niagara River.
- Mamaroneck Wastewater Treatment Plant BNR Upgrades: Westchester County. $51.0 million, clean water, $22.9 million in grants and forgiven principal. Sept. 1, 2009. STP UP [NUTRIENT REMOVAL (SLI-01)] Contract SLI-01 Long Island Sound nutrient removal. the order on consent is for the Mamoroneck, New Rochelle, Blind Brook, and Port Chester Sewer Districts, this project pertains to…
- BINGHAMTON AND JOHNSON CITY: Binghamton - Johnson City. $45.0 million, clean water. May 11, 2023. STP REBUILD [C,N AND DN CELLS, FLOOD WALL, AND CEPT SYSTEM] Design and construction of a project to rebuild components of the sewage treatment plant to improve the water quality in the Susquehanna and Chenango Rivers.
- Breckenridge, Baily, East Amherst, Gates Circle: Buffalo Sewer Authority. $43.6 million, clean water, $7.6 million in grants and forgiven principal. March 6, 2025. STP REHAB [Bird Island Wastewater Treatment Plant Primary - Phase 1] Planning, design, and construction of upgrades to the primary treatment system at the Bird Island Wastewater Treatment Plant to protect water quality…
- ONONDAGA LAKE IMPROVEMENT PROJECT (PH2): Onondaga County. $42.8 million, clean water. Sept. 29, 2011. CSO [HARBOR BROOK CSO ABATEMENT PHASE II] Elimination of combined sewer overflows as part of the Onondaga Lake Improvement Project to improve water quality in Onondaga Lake.
- NORTH RIVER: NYCMWFA. $42.7 million, clean water. June 16, 2022. STP MOD [NR-COGEN COGENERATION & ELECTRIFICATION] Project NR-COGEN. Planning, design, and construction of cogeneration facilities at the North River Wastewater Treatment Plant to protect water quality in the Hudson…
- VILLAGE OF BATH: Bath, Village of. $41.2 million, clean water, $17.5 million in grants and forgiven principal. Nov. 9, 2023. Planning, design, and construction of wastewater treatment plant improvements to improve water quality in the Cohocton River. STP MOD [DISINFECTION AND MISCELLANEOUS WWTP IMPROVEMENTS] Construction]
Counties that received the most
- Nassau: $531 million
- Suffolk: $358 million
- Oneida: $295 million
- Orange: $240 million
- Westchester: $227 million
- Onondaga: $209 million
- Wayne: $124 million
- Broome: $117 million
- Oswego: $111 million
- Chemung: $111 million
Every project, with filters, a map and a table, is on this page in the app. Source: EPA State Revolving Fund public records, through June 30, 2025.