Oregon
Where the state’s revolving fund money for water went, project by project.
$697 million committed to 328 drinking water and clean water projects.
- Drinking water: $285 million
- Clean water: $412 million
- Grants and forgiven principal: $101 million
- Latest agreement: June 23, 2025
The 25 largest projects
- Water Pollution Control Facility Treatment Plant Expansion: City of Redmond. $46.4 million, clean water, $500,000 in grants and forgiven principal. Aug. 2, 2021. In this design and construction loan, the Borrower will design and construct the Project, an aerated lagoon wetland treatment and disposal facility. The Project will include a headworks component for primary treatment,…
- Tri City Water Resource Recovery Facility Solids Handling Improvements Project: Water Environment Services. $37.0 million, clean water. Jan. 15, 2019. Project includes installation of an anaerobic digester, biosolids dewatering and cake loadout facility.
- Wastewater Treatment Plant SBR: City of Molalla. $33.3 million, clean water. July 2, 2024. The Borrower will convert facultative lagoon #2 of its wastewater treatment plant into a clay lined recycled water storage, reconstruct the aeration basin to provide influent flow equalization, upgrade the transfer…
- Wastewater Treatment Project: City of Coos Bay. $22.8 million, clean water, $500,000 in grants and forgiven principal. May 16, 2016. Design and construction of a new wastewater treatment facility including additional capacity and UV disinfection.
- North Transmission Intertie: City of Beaverton, Beaverton. $20.3 million, drinking water, $130,000 in grants and forgiven principal. Dec. 19, 2022. The Recipient will procure services to design and construct the North Transmission Intertie (?NTI?) line, consisting of 6.5 miles of seismically resilient 24-inch and 30-inch water main located in public rights-of-way…
- Pendleton Water System Improvements Final Design and Construction: City of Pendleton, Pendleton. $18.9 million, drinking water, $1.0 million in grants and forgiven principal. April 19, 2017. The Recipient shall, with the assistance of an Oregon-licensed professional engineer, complete Oregon Health Authority, Drinking Water Services-approved final design documents and construction of selected water system…
- Newport Corridor Improvements: City of Bend. $16.0 million, clean water. March 11, 2021. The city will reconstruct the existing drainage collection and conveyance system along Newport and Nashville Avenues from College Way to the outfall at the Deschutes River. Project elements include collection and…
- New Ashland 2.5-Million-Gallon Water Treatment Plant: City of Ashland, Ashland. $14.8 million, drinking water, $1.0 million in grants and forgiven principal. July 13, 2016. The Recipient will design and construct a new 2.5-MG drinking water treatment plant (capable of future expansion to 10 MG), on property owned by Recipient and identified in its application to IFA. The Project includes,…
- Wastewater Treatment Upgrades: City of La Pine. $13.0 million, clean water. March 2, 2020. The city will expand the collection system to Cagle and Glenwood Acres and replace septic tanks in the area. Upgrades to the wastewater treatment facility and disposal system include replacing the facilitys septage…
- Wastewater Treatment Plant Improvements: City of Molalla. $11.8 million, clean water, $500,000 in grants and forgiven principal. Oct. 6, 2020. Design loan to convert the facultative lagoons into lined recycled water storage, reconstruct the aeration basin to provide influent flow equalization, upgrade the transfer pump station, construct a new four cell…
- Power City/Brownell Sewer Service Extension: City of Umatilla. $10.8 million, clean water, $2.0 million in grants and forgiven principal. Jan. 17, 2025. This project will provide the residents of the Power City and Brownell communities with a reliable, public sewer utility system that is compliant with state and federal regulatory requirements. The project will consist…
- River Front Interceptor and Lift Station: City of Albany. $10.1 million, clean water. March 14, 2018. Rehabilitation of River Front Sewer Interceptor and construction of new wet weather lift station and force main project.
- Agate Beach Wastewater Collection System: City of Newport. $10.0 million, clean water. April 23, 2014. Upgrades to the Agate Beach wastewater collection system.
- Salishan SD MBR Install and Pump Stations Upgrade: Salishan Sanitary District. $10.0 million, clean water, $500,000 in grants and forgiven principal. April 22, 2021. The proposed project includes: design and construction of upgrades to the Borrower's sewage treatment plant that use membrane bioreactor technology, new plant headworks, replacement of five pumps and new control…
- Wastewater Treatment Upgrade: City of Dundee. $9.7 million, clean water. Dec. 28, 2010. This project will upgrade the wastewater treatment facility.
- Dog River Pipeline Replacement Project: City of The Dalles, The Dalles. $8.0 million, drinking water, $530,000 in grants and forgiven principal. Dec. 8, 2021. The Dalles will replace 3.5 miles of aged wooden pipeline to a ductile iron pipe, increase the capacity of pipeline to 17 MGD, improve their water metering systems, install fish screens, and construct/install screening…
- Awbrey Glen and Westside Pump Stations: City of Bend. $7.8 million, clean water, $1.0 million in grants and forgiven principal. June 29, 2023. "This Design and Construction project will rehabilitate two aging pump stations, the Awbrey Glen and Westside sanitary sewer pump stations. These pump stations have documented hydraulic and condition deficiencies. This…
- Water System Backbone Resiliency Project Phase 3: City of Cannon Beach, Cannon Beach. $7.4 million, drinking water, $520,000 in grants and forgiven principal. Aug. 17, 2023. City will hire an engineering consultant licensed in the state of Oregon to complete the Design and Engineering phase in preparation for construction of new Main Reservoir and Pipeline Backbone between Main Reservoir…
- Wastewater Treatment and Collection System Improvement: City of Independence. $7.3 million, clean water, $500,000 in grants and forgiven principal. Dec. 6, 2017. Collection system upgrades Summer recycling of treated and disinfected effluent through spray irrigation on ag land
- Wastewater Treatment Plant Upgrades: City of Sandy. $7.3 million, clean water, $1.0 million in grants and forgiven principal. Aug. 2, 2023. The City of Sandy will upgrade the existing wastewater treatment plant (WWTP), which was placed into service in 1998, in order to comply with the NPDES permit for the current facility until the new facility is…
- Water System Improvements: City of Hines, Hines. $7.2 million, drinking water, $1.0 million in grants and forgiven principal. Oct. 11, 2018. The Recipient shall procure an engineer licensed in the State of Oregon to complete preliminary and final design and construction for this project. Supply improvements include replacing the Wells No. 2 and 3 well pump…
- Wastewater System Upgrades: City of Canyonville. $7.0 million, clean water. Aug. 15, 2016. Wastewater System and Riparian Upgrades.
- Water System Improvements: Johnson Creek Water Service Company, Newberg. $7.0 million, drinking water, $280,000 in grants and forgiven principal. Jan. 14, 2022. Recipient will design and construct the following priority improvements identified in the Johnson Creek Water Service Co. Water Master Plan, dated September 2020, including: ? Construct a new water treatment plant with…
- Agate Beach Wastewater Collection System (1 of 1): City of Newport. $7.0 million, clean water. Aug. 28, 2018. Increase to loan R68933
- Water Infrastructure Projects: City of Rogue River, Rogue River. $6.9 million, drinking water, $530,000 in grants and forgiven principal. Nov. 4, 2021. The City of Rogue River will complete construction according to the final design plans, which will include, but is not limited to: ? Construction of a new 1.0 MG concrete ground water reservoir; ? Installation of…
Counties that received the most
- Deschutes: $133 million
- Clackamas: $119 million
- Umatilla: $46.4 million
- Jackson: $42.6 million
- Washington: $36.8 million
- Lincoln: $24.3 million
- Douglas: $21.8 million
- Hood River: $20.9 million
- Yamhill: $19.2 million
- Polk: $18.7 million
Every project, with filters, a map and a table, is on this page in the app. Source: EPA State Revolving Fund public records, through June 30, 2025.